A Gantt-style programme of activities with dependencies, working-day durations, milestones and percent complete for the whole build.
Sign in with your Edesy account, then click Use template in the preview to copy the base, with its sample rows, into your workspace.
Category
Tables
Activities
Fields
12
Views
grid, timeline, kanban, calendar
The table in this template, with its real columns, field types and sample rows. Copy the template to edit it in Edesy Tables.
12 fields · 8 sample rows
| ActivityText | PhaseSingle select | StartDate | FinishDate | Working daysFormula | Crew / contractorText | Depends onLink to another table | % completePercent | StatusSingle select | MilestoneCheckbox | Days to finishFormula | NotesText |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Site mobilisation | Mobilisation | 10 Sep 2026 | 17 Sep 2026 | 6 | Main contractor | 100% | Complete | ||||
| Excavation | Substructure | 18 Sep 2026 | 5 Oct 2026 | 12 | Earthmovers India | Site mobilisation | 100% | Complete | |||
| Raft foundation | Substructure | 6 Oct 2026 | 30 Oct 2026 | 19 | Solid Base Constructions | Excavation | 100% | Complete | Yes | ||
| Ground floor columns & slab | Superstructure | 31 Oct 2026 | 24 Nov 2026 | 17 | Skyward Structures | Raft foundation | 70% | In progress | 5 | ||
| First floor columns & slab | Superstructure | 25 Nov 2026 | 19 Dec 2026 | 18 | Skyward Structures | Ground floor columns & slab | 0% | Not started | 30 | ||
| Electrical conduiting | MEP | 14 Nov 2026 | 29 Dec 2026 | 32 | Volt Electricals | Ground floor columns & slab | 10% | Delayed | 40 | Drawings revision pending | |
| Brickwork & plaster | Envelope | 20 Dec 2026 | 2 Feb 2027 | 32 | Main contractor | First floor columns & slab | 0% | Not started | 75 | ||
| Structure topped out | Superstructure | 19 Dec 2026 | 19 Dec 2026 | 0 | First floor columns & slab | Not started | Yes | 30 |
Yes. Copy the template, then import a .csv, .tsv or .xlsx file into any of its tables and map the columns. Delete the sample rows first if you do not need them.
Yes. An automation runs when a record is created, updated or matches a filter, when a form is submitted, on a schedule or when a date arrives, and can update or create records, call a webhook or post to a connected Slack channel.
Line up subcontractor bids for each work package side by side — price with tax, duration, warranty and score — and award the best one.
2 tables · 24 fieldsBid Tabulation TemplateA classic bid tab: each BOQ line priced by three bidders against the engineer’s estimate, with extended totals and the lowest bidder per line.
1 table · 15 fieldsBill of Materials TemplateEvery component needed for a build with quantity, unit cost, extended cost and order status, tied to suppliers and their lead times.
2 tables · 23 fieldsClient List TemplateA tidy list of every client for any service business — contact details, visits, spend and how long since you last saw them.
1 table · 16 fieldsConstruction Budget TemplateCost-code budget for a build: original budget plus change orders, committed and actual cost from invoices, and overrun warnings per line.
2 tables · 21 fieldsConstruction ChecklistPhase-by-phase site checklist from pre-construction to handover, with owners, due dates, required inspections and photo proof.
1 table · 10 fields