A project risk register with cause and effect, probability and impact scales, financial exposure, and linked mitigation actions.
Sign in with your Edesy account, then click Use template in the preview to copy the base, with its sample rows, into your workspace.
Category
Tables
Risks, Actions
Fields
24
Views
grid, kanban, dashboard, calendar
The 2 linked tables in this template, with their real columns, field types and sample rows. Copy the template to edit them in Edesy Tables.
17 fields · 5 sample rows
| RiskText | RefAutonumber | ProjectSingle select | CauseLong text | EffectLong text | ProbabilitySingle select | ImpactSingle select | ScoreFormula | LevelFormula | ExposureCurrency | Expected LossFormula | ProximitySingle select | OwnerText | StatusSingle select | ActionsLink to another table | Action CountCount | Open ActionsRollup |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Data migration errors | RR-01 | ERP rollout | Legacy data has duplicates and missing codes. | Wrong stock and ledger balances at go-live. | Likely | Major | 16 | Extreme | ₹25,00,000 | ₹17,50,000 | Within 3 months | Sunita (PMO) | Treating | Run data cleansing sprint, Two mock migrations with sign-off | 2 | 2 |
| Monsoon delays civil works | RR-02 | New plant – Chakan | Heavy rain June–Sept. | Commissioning slips by 6–8 weeks. | Possible | Moderate | 9 | Medium | ₹40,00,000 | ₹20,00,000 | Within 6 months | Vikram (Projects) | Monitoring | Pre-book covered work areas | 1 | 1 |
| App store rejection | RR-03 | Mobile app v3 | New payment flow may break store guidelines. | Launch delayed. | Unlikely | Moderate | 6 | Medium | ₹6,00,000 | ₹1,20,000 | Immediate | Grace (Product) | Identified | 0 | 0 | |
| Key consultant leaves | RR-04 | ERP rollout | Single SME holds finance config knowledge. | Configuration stalls. | Possible | Severe | 15 | Extreme | ₹18,00,000 | ₹9,00,000 | Within 6 months | Sunita (PMO) | Treating | Document finance configuration | 1 | 1 |
| Equipment import customs hold | RR-05 | New plant – Chakan | Classification dispute on CNC machines. | Installation idle time. | Rare | Major | 4 | Low | ₹12,00,000 | ₹60,000 | Within 3 months | Vikram (Projects) | Closed | Advance customs ruling | 1 | 0 |
7 fields · 5 sample rows
| ActionText | RiskLink to another table | OwnerText | Due DateDate | StatusSingle select | CostCurrency | Is OpenFormula |
|---|---|---|---|---|---|---|
| Run data cleansing sprint | Data migration errors | Data team | 3 Dec 2026 | In progress | ₹1,50,000 | 1 |
| Two mock migrations with sign-off | Data migration errors | Sunita | 29 Dec 2026 | Not started | 1 | |
| Document finance configuration | Key consultant leaves | Consultant | 29 Nov 2026 | In progress | 1 | |
| Pre-book covered work areas | Monsoon delays civil works | Vikram | 19 Dec 2026 | Not started | ₹3,00,000 | 1 |
| Advance customs ruling | Equipment import customs hold | Logistics | 9 Nov 2026 | Done | ₹40,000 | 0 |
Yes. Copy the template, then import a .csv, .tsv or .xlsx file into any of its tables and map the columns. Delete the sample rows first if you do not need them.
Yes. An automation runs when a record is created, updated or matches a filter, when a form is submitted, on a schedule or when a date arrives, and can update or create records, call a webhook or post to a connected Slack channel.
Log what you worked on, when and for how long, then see where your hours really go by category and project.
1 table · 10 fieldsAnger Management SheetA private anger journal: note what triggered it, how intense it felt, what you did to cope and how much it helped.
1 table · 12 fieldsBathroom Cleaning LogA contactless restroom cleaning log: staff scan, tick what they cleaned and restocked, and supervisors spot missed checks.
1 table · 10 fieldsCall Log TemplateA sales call log that ties every call to a contact, records direction, duration and outcome, and schedules the follow-up.
2 tables · 20 fieldsCase Management SheetTrack client cases from intake to closure, with caseworker assignments, next actions, documents and a dated log of every contact.
2 tables · 26 fieldsChange Log TemplateRecord every product or project change — what changed, why, who approved it, the release it shipped in and how to roll it back.
1 table · 15 fields