Critical Path Template

Map task dependencies and keep the critical path visible so delays show up before they hit the end date.

Sign in with your Edesy account, then click Use template in the preview to create the board, with its sample cards, in your workspace.

Category

Project & Task ManagementProject Planning

Ideal for

Professional ServicesEngineering & Product TeamsOperations & Logistics Teams

Columns

Not started → Ready (dependencies met) → In progress → Slipping → Completed

Sample cards

7

Custom fields

Duration (days), Slack (days)

Request form

Creates cards in Not started

Columns and sample cards

The 5 columns of this board with its 7 sample cards, labels and fields, as they open in Edesy Boards. Copy the template to move cards and edit it.

  1. Not started

    2
    • A: Site surveyPriority: highCritical path
      Duration (days):
      3
      Slack (days):
      0
    • B: Design approval (needs A)Priority: mediumCritical pathDependency
      Duration (days):
      5
      Slack (days):
      0
      Checklist 0/4: Define scope, Agree owner, Set deadline, Share with stakeholders
  2. Ready (dependencies met)

    1
    • C: Order long-lead equipment (needs B)Priority: urgentCritical path
      Duration (days):
      8
      Slack (days):
      8
  3. In progress

    1
    • D: Staff training planPriority: lowHas slack
      Duration (days):
      4
      Slack (days):
      6
  4. Slipping

    2
    • E: Installation (needs C)Supplier delay of 2 days moves the end date.Priority: urgentCritical path
      Duration (days):
      13
      Slack (days):
      13
      Checklist 3/4: Draft, Review with team, Revise, Sign-off
    • F: Commissioning and handoverPriority: mediumMilestone
      Duration (days):
      1
      Slack (days):
      1
  5. Completed

    1 · done stage
    • Recalculate path after supplier delayPriority: highDependency
      Duration (days):
      4
      Slack (days):
      4

Labels

Critical path, Has slack, Dependency, Milestone

Custom fields

Duration (days) (Number, on card), Slack (days) (Number, on card)

Request form: Request a task · Critical Path

Tell us what you need; it lands on the “Not started” column of this board. Asks for Title, Description, Priority, Due date, Attachments; each submission becomes a card in Not started.

Card templates

Milestone

Critical Path Template: questions

Yes, through the board request form. Share its public link; each submission becomes a card in the chosen column, with the answers in the card fields. Viewers of a shared read-only board link can see the board without an account.

Yes. Board automations run when a card is created, moved, assigned, labelled, completed, due soon or overdue, when a form is submitted or on a schedule, and can move, assign, label or archive the card, add a checklist or comment, create another card, call a webhook or post to Slack.

Related templates